Necessary measures to ensure safety and properties of the project
(Brac University, 2020-03-21) -
Necessary precautions during removing site materials
(Brac University, 2020-10-05) -
Nerothane PU topcoat color and TDS on PV steel roof under contact no.: BRACU/New Campus/2022/482 (RFA-006)
(Brac University, 2023-01-04) -
Nerothane PU topcoat color and TDS on PV steel roof under contact no.: BRACU/New Campus/2022/482 (RFA-006_Rev. A)
(Brac University, 2023-04-01) -
New cat walk beams and grating layout plan_ Rev A
(Brac University, 2023-02-06) -
New catwalk sections and details_Rev A
(Brac University, 2023-02-06) -
Nomination to visit China
(Brac University, 2018-11-15) -
Non tender work for daily worker and equipment
(Brac University, 2018-08-06) -
Non-deduction from running bill no. 009
(Brac University, 2019-06-10) -
Normal staircase
(Brac University, 2021-09-30) -
North entrance (Architectural As Built Drawings)
(Brac University, 2023-07-01) -
North Entrance (RFA-510_Rev B )
(2022-09-23) -
North entrance cable ( RFA-470_Rev A)
(Brac University, 2022-10-28) -
North entrance cable ditch (RFA-470_Rev.A)
(Brac University, 2022-02-28) -
Note of discussion and decision
(Brac University, 2018-07-31)A meeting among the representatives of BRAC University, the Engineer, WOHA, WEB, the Contractor and the Bracing Design Team was held at 10:00 AM on 31th July 2018. -
Notice for additional service of cooperating the D-wall tester
(Brac University, 2018-05-20) -
Notice for additional work of king post pile
(Brac University, 2018-04-05) -
Notice for additional work of King Post Pile
(Brac University, 2018-04-16) -
Notice for additional work of shoring pile work
(Brac University, 2018-02-13) -
Notice for additional work of the steel sheath for one foundation pile
(Brac University, 2018-04-10)