Request to issue site instruction for draining box around building ground of BRAC University new campus project
(Brac University, 2019-10-06)
Closed design of the 5th batch member sizes and materials of BRAC University new campus project
(Brac University, 2019-04-01)
VO #015 Revised proposal of 500mm Dia bored pile works rev. 01
(Brac University, 2019-12-17)
IT workshop meeting with SDG/WOHA
(Brac University, 2019-08-08)
Meeting notes of workshop between WOHA and SDG held at WOHA office on 05 August 2019.
Work Interface of high voltage electrical and IFC drawings of BRAC University new campus project
(Brac University, 2019-06-23)
Minutes of 22nd technical and progress monitoring (TPM) meeting of BRACU new campus (session II)
(2019-10-31)
The 22nd TPM (session ll) meeting was held at 11:00 AM on 31 October 2019 with Mr. A.S.M Rashidul Hai, Project Director, BRACU new campus project in the Chair. The Chair welcomed all participants and commenced the business ...
Letter about income tax return problem for short challan
(Brac University, 2019-11-06)
Reasons for replacing brand of waterproof materials of BRAC University new campus project
(Brac University, 2019-01-20)
EP section=04A of BRAC University new campus project
(Brac University, 2019-04-20)
Issuing NCR (Non-conformance report) for BRACU new campus project
(Brac University, 2019-12-24)