Browsing 2021 by Author "BUCG-ABC Joint Venture"
Now showing items 1-20 of 24
-
Application for the refund of the temporary substation fee returned by DESCO
BUCG-ABC Joint Venture (Brac University, 2021-11-10) -
Instruction to maintain a healthy environment
BUCG-ABC Joint Venture (Brac University, 2021-06-08) -
Interim payment application no. 023 (Part-B)
BUCG-ABC Joint Venture (Brac University, 2021-03-22) -
Monthly progress report of March 2021 of BRAC University new campus project
BUCG-ABC Joint Venture (Brac University, 2021-04-07) -
Monthly progress report of November 2021 of BRAC University new campus development project
BUCG-ABC Joint Venture (Brac University, 2021-11-04) -
Monthly progress report of October 2021 of BRAC University new campus development project
BUCG-ABC Joint Venture (Brac University, 2021-10-04) -
Monthly progress report of September 2021 of BRAC University new campus development project
BUCG-ABC Joint Venture (Brac University, 2021-10-04) -
Receipt of the authorization letter of work order for the acknowledgement of BUCG
BUCG-ABC Joint Venture (Brac University, 2021-01-24) -
Reference level marking on each floor of BRAC University new campus project
BUCG-ABC Joint Venture (Brac University, 2021-08-17) -
Regarding emergency RMC supply for BRAC University new campus project
BUCG-ABC Joint Venture (Brac University, 2021-04-29) -
Regarding landscape works of BRAC University new campus project
BUCG-ABC Joint Venture (Brac University, 2020-03-18) -
Request of fund support
BUCG-ABC Joint Venture (Brac University, 2021-10-25) -
Request to open new work order for the steel structure work of BRAC University new campus project
BUCG-ABC Joint Venture (Brac University, 2021-01-05) -
Resubmission of the adjustment unit price for VO #09 prefabricated steel structure with grade alternation from S355J0 to S355ML & S460ML
BUCG-ABC Joint Venture (Brac University, 2021-06-18) -
Resubmission of valuation for siphonic system (rev. 04) of BRAC University new campus project
BUCG-ABC Joint Venture (Brac University, 2021-01-24) -
The updated performance guarantee (original copy)
BUCG-ABC Joint Venture (Brac University, 2021-07-28) -
VO #032 Valuation of embedded parts and junction box for MEP works (Rev. 04)
BUCG-ABC Joint Venture (Brac University, 2021-03-21) -
VO #033 Proposal of 800mm Dia shoring piles works at zone C of BRAC University new campus project
BUCG-ABC Joint Venture (Brac University, 2021-01-05) -
VO #034 Supply installation, testing & commissioning of ESE lighting protection system (rev.00)
BUCG-ABC Joint Venture (Brac University, 2021-02-22) -
VO #034 Supply installation, testing & commissioning of lighting protection system (rev.01)
BUCG-ABC Joint Venture (Brac University, 2021-03-15)