Pre-qualification documents for waterproofing subcontractor
(Brac University, 2018-04-10)
Application for 20% of the L/C price of the first batch steel members
(Brac University, 2019-05-23)
Lack of drawings for quotation preparation
(Brac University, 2019-06-22)
Notice for additional works of steel sheath removal for one foundation pile
(Brac University, 2018-04-08)
Notice for additional work of waterproofing work for retain wall and capping beam
(Brac University, 2018-03-12)
The status of MEP IFC drawing
(Brac University, 2019-04-04)
Master schedule of BRAC University new campus development project
(Brac University, 2019-09-22)
BRAC University new campus development project construction schedule (July, 2019- September, 2019)
(Brac University, 2019-04-29)
Request for confirmation concerning valuation for cutting rebar of foundation piles
(Brac University, 2018-05-20)
Response to engineer's letter Ref. BRACU-NCP-2018 25A & 26A