Utility building portion
(Brac University, 2021-03-25)
Request of closing the outstanding issues of design services of BUCG for BRAC University new campus project
(Brac University, 2021-11-04)
Ground floor slab, beam and column
(Brac University, 2021-10-21)
The 4th interim payment application under design contract of BRAC University new campus project
(Brac University, 2021-06-19)
Pilecap And Raft - Basement 3 ( Zone A & zone C)
(Brac University, 2021-01-16)
Postponing some services from the design services of BUCG
(Brac University, 2021-04-13)
The impact of failure to perform the design contract of BRAC University new campus project
(Brac University, 2021-04-22)
Request meeting for resolving the performance problem of the design contract of BRAC University new campus project
(Brac University, 2021-03-24)