Search
Now showing items 11-20 of 201
Submission of contractor's all risk (CAR) insurance
(Brac University, 2020-12-30)
Re: Regarding rebar requisition no. M-38 and M-39
(Brac University, 2020-07-08)
Re: Missing of scrap materials from project site
(Brac University, 2020-06-25)
Regarding issues that affect the execution of permanent retaining wall
(Brac University, 2020-02-26)
The 7th submission of manpower and machinery & equipment for BRACU project
(Brac University, 2020-07-01)
The 6th submission of manpower and machinery & equipment for BRACU project
(Brac University, 2020-06-15)
Regarding the 33/11KV substation (external substation) and temporary substation (internal substation)
(Brac University, 2020-08-27)
Application for 20% of the L/C price of the 11th to 15th batch steel members
(Brac University, 2020-08-05)
Request to again release payment upon R/B 017
(Brac University, 2020-04-21)
Monthly progress report of November, 2020 of BRAC University new campus development project
(Brac University, 2020-12-15)