Interim payment application no. 009
(Brac University, 2019-05-29)
Revised proposal for additional wall attached to diaphragm wall of BRAC University new campus project
(Brac University, 2019-10-07)
Proposal resubmission of VO #09 & 010 for steel structure works of BRAC University new campus project
(Brac University, 2019-11-25)
Clarification for the master construction schedule of BRAC University new campus project
(Brac University, 2019-04-17)
Proposal of rebar welding works connected to plate of steel column of BRAC University new campus project
(Brac University, 2019-08-04)
Request to not adjust advance payment under running bill no. 009 and request of money borrow
(Brac University, 2019-05-30)
Request to fix VAT & AIT rate as 7% for additional works of BRAC University new campus project
(Brac University, 2019-10-08)
Monthly progress report of November 2019 of BRAC University new campus project
(Brac University, 2019-12-22)
VO #024 Proposal of temporary beams being changed to permanent works