Performance of public works department in procurement activity compliance to PPA-2006, & PPR -2008
View/ Open
Date
2016-09Publisher
BRAC UniversityAuthor
Rahman, SK. ToufiqurMetadata
Show full item recordAbstract
Transparency, efficiency, accountability, competitiveness, equitable treatment and free &
fair competition are essential to be ensured in the procurement using public funds. In
Bangladesh, these could not be ensured earlier due to a lack of proper rules and regulation.
To streamline the public procurement activities, the Government of the People’s Republic
of Bangladesh has enacted Public Procurement Act (PPA) 2006 and thereafter issued Public
Procurement Rules (PPR) 2008. Since then government agencies are bound to abide by the
Act and Rules very strictly in their procurement activities. The Central Procurement
Technical Unit (CPTU) of the Implementation Monitoring and Evaluation Division (IMED) is
continually monitoring the compliance of PPA 2006 and PPR 2008 by the target agencies in
the light of 45 predetermined Key Performance Indicators (KPI).In spite of being a major procuring agency of the country PWD is not among the four target
agency. At the time of selection of the target agency the amount of procurement in PWD is
not in the first four. But after that the amount of procurement has increased substantially.
Now PWD has procured more than Water development Board (one of the four target
agency).monitored keenly. Now it is required to take a look on PWD’s procurement activities.
The research has been designed under the questions if PWD is following PPR 2008
completely or not; and if not, then the causes behind that. The main objectives of the
present study are to find out the extent of compliance of PPR 2008 by PWD and to find out
the gap of compliance and scope of improvement for implementation. The related
literatures and reports, particularly from PWD and SRGB, have been thoroughly reviewed
before conducting the main research work. The key findings of these reports have been
compared and analyzed which helped to draw important conclusion of the study.A questionnaire survey was carried out to collect data of different projects undertaken by
PWD. The study result shows a clear noncompliance to the rules of PPR 2008 in PWD in
carrying out some of the compliance related KPIs. Among the 11 different compliance
issues, it has been revealed that PWD is doing well in 7 KPIs. For other 4 issues namely
submission of report by the TEC, Average number of days taken between submission of
Tender Evaluation Report and approval of contract, Average number of days between final
approval and Notification of Award (NOA) and Percentage of Contracts where interest for
delayed payments was made are not satisfactory and a clear improvement is required in
these areas.For improvement of these situations, some specific recommendations have been drawn.
These are (i) Compiling the contractors profile (ii) Empowering the lower tier will decrease
the time in approval process (iii) Strong adherence of law and effective internal auditing
(iv) Payment of interest in case of delayed payment should be considered carefully to
protect the interests of both the parties. (v) Introduction to e-GP (vi) Training on
Procurement law (vii) to ensure the timely payment to the contractors, tender should be
floated only after availability of sufficient fund.