Reminder of high strain dynamic load test for piles of BRAC University new campus project
(Brac University, 2019-04-25) -
Adjustment unit price for planting reinforcement work of BRAC University new campus project
(Brac University, 2019-04-28) -
Adjustment unit price for dam proofing works in Raft, Pile Cap, H-steel and King Post of BRAC University new campus project
(Brac University, 2019-04-28) -
Adjustment unit price for pile splicing work of BRAC University new campus project
(Brac University, 2019-04-28) -
Request for amplifying municipal power supply
(Brac University, 2019-04-13) -
The status of MEP IFC drawing
(Brac University, 2019-04-04) -
Monthly progress report of March 2019 of BRAC University new campus project
(Brac University, 2019-04-04) -
Closed design of the 5th batch member sizes and materials of BRAC University new campus project
(Brac University, 2019-04-01) -
Approved waterproof membrane as per RFA 80
(Brac University, 2019-04-02) -
Reply to instruction to submit cash flow estimate of BRAC University new campus project
(Brac University, 2019-03-30) -
Cost analysis of breaking unforeseeable piles of BRAC University new campus project
(Brac University, 2019-03-28) -
Reply to shipment of pre-fabricated steel structure against LC no. 0000021619010057
(Brac University, 2019-04-28) -
Validation for instrumentation and monitoring works of BRAC University new campus project
(Brac University, 2019-03-24) -
Reply to shipment of pre-fabricated steel building of BRAC University new campus project
(Brac University, 2019-03-25) -
Suggestion about structure pile test
(Brac University, 2019-03-21) -
Regarding cement brand of jet grouting pile
(Brac University, 2019-03-19) -
Further clarification on amendment of earth excavation depth
(Brac University, 2019-03-11) -
Resubmission of valuation for instrumentation and monitoring works of BRAC University new campus project
(Brac University, 2019-03-08) -
Regarding mix design of the concrete of BRAC University new campus project
(Brac University, 2019-03-07) -
Request to amendment of earth excavation