Evaluation for additional work of sharing pile work between zone A and zone C – 05.04.18
(Brac University, 2018-04-05) -
Evaluation for additional work of shoring pile work in zone B
(Brac University, 2018-04-02) -
Evaluation for additional work of shoring pile work in zone B
(Brac University, 2018-04-02) -
Evaluation for additional work of waterproofing on the retaining wall and capping beam
(Brac University, 2018-04-18) -
Evaluation for additional work of waterproofing on the retaining wall and capping beam
(Brac University, 2018-04-18) -
Expenditure statement payment of advance payment
(Brac University, 2018-11-06) -
Insurance (CAR) for the project
(Brac University, 2018-05-13) -
The interim application of EOT from 16 July , 2018 to 12 August 2018
(Brac University, 2018-08-21) -
The interim application of EOT from 18 June , 2018 to 15 July 2018
(Brac University, 2018-07-16) -
The Interim application of EOT from 23” April, 2018 to 20''‘ map 2018 our Ref: BUCG-ABC JV-JAA-014
(Brac University, 2018-06-05) -
Interim payment application .003
(Brac University, 2018-08-08) -
Interim payment application no. 002
(Brac University, 2018-06-05) -
Interim payment application no. 006
(Brac University, 2018-12-13) -
Interim payment application no.004
(Brac University, 2018-10-04) -
Interim payment application no.005
(Brac University, 2018-11-30) -
L/C for pre-engineering steel sections
(Brac University, 2018-11-13) -
Monthly progress report of December of Brac University new campus development project
(Brac University, 2019-01-10) -
Monthly progress report of December of Brac University new campus development project
(Brac University, 2019-01-10) -
Monthly progress report of July of Brac University new campus development project
(Brac University, 2018-08-07)