Instruction to submit cash flow estimate
(Brac University, 2019-03-16) -
Shipment of pre-fabricated steel building (Shipment of steel structure against LC no. 0000021619010057 dated: 26.02.19)
(Brac University, 2019-03-27) -
Suggestion about structure pile test
(Brac University, 2019-03-27) -
Response to RFA 095 regarding approved sample of membrane
(Brac University, 2019-03-31) -
Engineer’s instructions to submit method statement for construction of 300mm additional wall
(Brac University, 2019-04-04) -
Cost analysis of breaking unforeseeable piles
(Brac University, 2019-04-04) -
Engineer’s instructions to submit work methodology
(Brac University, 2019-04-07) -
Request for payment of outstanding amount and issue of work completion certificate for piling and D-wall
(Brac University, 2019-04-15) -
Submission of three months’ work schedule
(Brac University, 2019-04-16) -
Submission of updated master schedule
(Brac University, 2019-04-16) -
VO#12 - Adjustment unit price for damp proofing work in raft, pile cap, H-steel and king post
(Brac University, 2019-04-19) -
Bill payment to NSL for BRACU new campus project
(Brac University, 2019-04-27) -
Clarification for the master construction schedule
(Brac University, 2019-04-27) -
Damaging the road of Dhaka north city corporation (DNCC)
(Brac University, 2019-04-29) -
Approval of instrumentation & monitoring works
(Brac University, 2019-04-29) -
Vo#9 Adjustment unit price request for prefabrication steel structure works
(Brac University, 2019-04-29) -
Construction production be adversely affected by modification of original design
(Brac University, 2019-04-29) -
Approval for extra rates for earth work in excavation for unforeseeable piles
(Brac University, 2019-04-30) -
VO.11 - Adjustment of unit price for pile splicing work