Instruction to engage more workers to complete works as contract and schedule
(Brac University, 2022-05-11) -
Consideration in the electrical system design work
(Brac University, 2019-12-04) -
Instruction to ensure safety & security at BRACU new campus project (NS Construction)
(Brac University, 2022-03-27) -
Issues for before plaster and tiles work of BRAC University new campus project
(Brac University, 2022-01-04) -
Regarding change/repair of PFI plant
(Brac University, 2022-03-13) -
Regarding fire incidents and further precaution
(Brac University, 2022-03-20) -
The engineer's observation and instruction regarding health of the personnel
(Brac University, 2019-11-09) -
PFI Plant মেরামত প্রসঙ্গে
(ব্র্যাক বিশ্ববিদ্যালয়, 2022-03-24) -
Regarding marking and physical mock-up for your services (BTCL)
(Brac University, 2022-03-23) -
Regarding marking and physical mock-up for your services (Tritech)
(Brac University, 2022-03-23) -
Regarding proforma invoice amounts and negotiated amount of HVAC works
(Brac University, 2022-05-16) -
ব্র্যাক বিশ্ববিদ্যালয়ে নতুন ক্যাম্পাসের ৫০০০ কিলোওয়াট লোড ছাড়পত্রের মেয়াদ বর্ধিতকরণ প্রসঙ্গে
(ব্র্যাক বিশ্ববিদ্যালয়, 2022-10-02) -
Regarding progress of ledge works
(Brac University, 2022-05-25) -
Rejected tiles-type TL-1 - TL-2, supplying of 2nd consignment of tiles TL-1 and TL-2 and supplying 1st lot of tile type TL-6
(Brac University, 2022-06-16) -
Reminder to submit cash flow estimates
(Brac University, 2022-05-16) -
Reply regarding resolving the issue of VO # 09
(Brac University, 2022-04-22) -
Pending items needed submissions from BUCG
(Brac University, 2022-06-20) -
Request of closing the outstanding issues of design services of BUCG
(Brac University, 2021-11-03) -
Regarding method statement of painting work on classroom ceiling (CC4)
(Brac University, 2022-06-15) -
Submission of monthly progress report
(Brac University, 2022-05-16)