Browsing Brac University New Campus Development Project by Title
Now showing items 2360-2379 of 2622
-
Unit breakdown for additional items
(Brac University, 2019-07-25) -
Unit price approval-planting reinforcing works
(Brac University, 2019-05-13) -
Unloading of 5th consignment shipment of prefabricated steel building
(Brac University, 2019-07-16) -
Up roof column detail layout plan_Rev A
(Brac University, 2023-02-06) -
Up roof section layout plan-sheet 1_Rev A
(Brac University, 2023-02-06) -
Up roof section layout plan-sheet 2_Rev A
(Brac University, 2023-02-06) -
Update regarding power connection for temporary 1000 KW load
(Brac University, 2020-08-25) -
Updated 6F-12F floor finish (RFA-544_Rev.A)
(Brac University, 2022-10-19) -
The updated performance guarantee (original copy)
(Brac University, 2021-07-28) -
Upper roof (jogging track slab)
(Brac University, 2022-03-20) -
Upper roof anchor bolt_Rev A
(Brac University, 2023-02-06) -
Upper roof and PV roof RCC structure drawing (RFA-474_Rev.B)
(Brac University, 2022-03-20) -
Upper roof column layout plan 1-3_Rev A
(Brac University, 2023-02-06) -
Upper roof floor tiles layout and finishes plan (RFA-506_Rev.B)
(Brac University, 2022-07-15) -
Upper roof hanger and anchor layout plan_Rev A
(Brac University, 2023-02-06) -
Upper roof wall change (RFA-474_Rev C)
(Brac University, 2022-07-29) -
Upturn wall near the escalator void at roof level (RFA-532_Rev.A)
(Brac University, 2022-10-02) -
Urgent attention from BUCG to help expedite progress for the lift and escalator work of BRAC University new campus project
(Brac University, 2022-06-04) -
Use of BRACU supplied cement and rebar in the work other than BOQ item no. 5.1, 7.1.2, 7.2.5. and 5.2, 7.1.4, 7.2.6
(Brac University, 2022-05-16)